               PROJECT
                21         Reverse Osmosis System


                           Target Date : 2022
                           Targets and Actions: The use of a reverse osmosis unit in the steam boiler of the Dyehouse factory
                           prevents the accumulation of solids and crystals in the water and preserves the heat in the boiler.
                           Approximately 10 m3/day of water is recovered at the Dyehouse factory.
                           In 2020, a reverse osmosis unit started to be used in the Spinning factory during the treatment of
                           water in the treatment unit. The suggestion of the month by our employees was that 50% of the
                           water used in the reverse osmosis unit could not be treated, and that 50% of the untreated water
                           should be reused by giving it to the reverse osmosis unit. This proposed project was commissioned
                           in 2022, saving 25 m3/day of water.
                           Results:
                           Environmental :
                           • 35 m3/day water savings
                           • Water saving
                           • Heat savings


               PROJECT
                22         Dyehouse Factory - New Machinery Investments


                           Target Date : 2022
                           Actions: 3 water jets in the Dyehouse factory were replaced with air jets that consume less water
                           and added to the machine park.
                           Results:
                           Environmental:
                           • 15% water savings




               PROJECT
                23         Dyehouse Factory - RAM Water Recovery

                           Target Date : 2023
                           Actions: Our aim is to reuse the foulard water generated as a result of the operation of the foulard
                           cylinder used in finishing and dyeing processes in production processes. It is planned to start wor-
                           king on the reuse of the pile that passes from the processed fabric into the water by separating it
                           from the scarf water.
                           Results:
                           Environmental:
                           • Water saving




               PROJECT
                24         Dyehouse Factory - Use of Wet Opening Water

                           Target Date : 2023
                           Actions: Our aim is to include the water generated during the wet opening process in the Dyehou-
                           se factory production line into the production. It is planned to start project studies for water
                           recovery to be realized by installing a filter - sieve system that allows the cleaning of fabric pile in
                           the water.
                           Results:
                           Environmental:
                           • Water saving


                                                                                           GRI 2-24, GRI 3-3, GRI 303-1  119